Project Description:
CUMMINGTON- BRIDGE PRESERVATION, C-21-002, ROUTE 9 OVER WESTFIELD RIVER
Location:
  • Town of Cummington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $8,530,442.35
    Estimated Total Federal Participating Construction Cost: $8,838,459.28
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 1
    Current Status: Final Package to FAPRO (as of 06/12/2025 )

    Contracts (1) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CUMMINGTON
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $7,066,468.80
    State Cost: $1,766,617.20
    Total Cost: $8,833,086.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/16/2021
    Project Initiation Form PIF Entered 10/01/2021
    Project Initiation Form PRC Submitted 10/18/2021
    Project Review Committee PRC Approved 10/21/2021
    Project Management
    100% Design 100% Package Received 12/15/2023
    100% Design 100% Package Comments to DE 01/22/2024
    75% Design 75% Package Received 08/06/2023
    75% Design 75% Package Comments to DE 10/10/2023
    75% Design 75% Package Rejected 10/10/2023
    75% Design 75% Package Received - Resub 1 11/08/2023
    Final Design PS&E Received 03/26/2024
    Final Design PS&E to FAPRO 06/12/2025
    Final Design PS&E Received - Resub 1 05/16/2024
    Final Design PS&E Received - Resub 2 04/11/2025
    Consultant Contract Process Scope to DE 05/06/2022
    Consultant Contract Process NTP Issued 08/03/2022