Project Description: |
CHARLEMONT- BRIDGE REPLACEMENT, C-05-010, ROUTE 8A OVER DEERFIELD RIVER
The scope of work for this project consists of a full bridge replacement with a wider cross section that can accommodate at least one sidewalk and potential bikeways.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Summer 2027 |
Project Manager: | William F Brown |
Estimated Total Contract Cost: | $8,732,934.00 |
Estimated Total Federal Participating Construction Cost: | $9,056,376.00 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Franklin Regional Council of Governments. |
District: | District 1 |
Current Status: | The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 03/01/2023 ) |
|
Bridges
|
|
|
|