Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHARLEMONT- BRIDGE REPLACEMENT, C-05-010, ROUTE 8A OVER DEERFIELD RIVER
The scope of work for this project consists of a full bridge replacement with a wider cross section that can accommodate at least one sidewalk and potential bikeways.
Location:
  • Town of Charlemont
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: William F Brown
    Estimated Total Contract Cost: $8,732,934.00
    Estimated Total Federal Participating Construction Cost: $9,056,376.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 1
    Current Status: The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 03/01/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: CHARLEMONT
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $7,824,708.80
    State Cost: $1,956,177.20
    Total Cost: $9,780,886.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/16/2021
    Project Initiation Form PIF Entered 10/01/2021
    Project Initiation Form PRC Submitted 10/18/2021
    Project Review Committee PRC Approved 10/21/2021
    Project Management
    Consultant Contract Process Scope to DE 06/17/2022
    Consultant Contract Process Scope to DE 11/08/2022
    Consultant Contract Process Scope to DE 03/01/2023