| Project Description: |
BOSTON- BRIDGE REPLACEMENT, B-16-165, BLUE HILL AVENUE OVER RAILROAD
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Summer 2028 |
| Project Manager: | Paige Parker![]() |
| Estimated Total Contract Cost: | $62,532,325.00 |
| Estimated Total Federal Participating Construction Cost: | $65,487,175.00 |
| Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
| District: | District 6 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 06/14/2023 ) |
|
Bridges
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||