| Project Description: |
BROCKTON- IMPROVEMENTS ON FOREST AVENUE, FROM WEST STREET TO BREER STREET
Improvements will include bicycle accommodations and upgraded pedestrian infrastructure, plus geometric improvements at the Forest Avenue & West Street intersection, potentially including installation of a traffic signal or roundabout.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Jonathan E Freeman![]() |
| Estimated Total Contract Cost: | $8,483,400.00 |
| Estimated Total Federal Participating Construction Cost: | $8,778,450.00 |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||