Project Description:
CHELSEA- EVERETT- MEDFORD- REVERE- LITTER CONTROL, MOWING & VEGETATION MANAGEMENT ON ROUTE 16 (MYSTIC VALLEY PARKWAY/REVERE BEACH PARKWAY)
Location:
  • City of Chelsea
  • City of Everett
  • City of Medford
  • City of Revere
  • Construction Begins: Spring 2022
    Resident Engineer: Amir Pakyari
    Construction Bid Price: $301,203.55
    District: District 4
    Current Status: Litter removal and mowing/trimming is taking place on Route 16 from I-93 in Medford to Route 145 in Revere. (as of 09/12/2023)

    Contracts (1) Progress
    # 117412 -- Construction Contract
    Litter Control, Mowing & Vegetation Management on Route 16 (Mystic Valley Parkway/Revere Beach Parkway) 68% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/31/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Litter removal and mowing/trimming is taking place on Route 16 from I-93 in Medford to Route 145 in Revere.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2021
    Project Initiation Form PIF Entered 11/02/2021
    Project Initiation Form PRC Submitted 11/16/2021
    Project Review Committee PRC Approved 11/17/2021
    Project Status Advertised 02/19/2022
    Project Management
    100% Design 100% Package Received 12/13/2021
    Final Design PS&E Received 01/12/2022
    Final Design PS&E to FAPRO 01/26/2022