Project Description:
DENNIS- YARMOUTH- BRIDGE REPLACEMENT, D-07-004=Y-01-003, ROUTE 28 OVER BASS RIVER INCLUDING INTERSECTION IMPROVEMENTS AT MAIN STREET(ROUTE 28)/NORTH MAIN STREET/OLD MAIN STREET
Location:
  • Town of Dennis
  • Town of Yarmouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Robert P Antico
    Estimated Total Federal Participating Construction Cost: $33,005,000.00
    District: District 5
    Current Status: 75% Package Received (as of 10/03/2022 )

    Contracts (1) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2021
    Project Initiation Form PIF Entered 11/17/2021
    Project Initiation Form PRC Submitted 11/23/2021
    Project Review Committee PRC Approved 11/29/2021
    Project Management
    25% Design 25% Package Received 10/03/2022
    75% Design 75% Package Received 10/03/2022