Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WELDED RAIL INSTALLATION AND MAINTENANCE ON THE CONNECTICUT RIVER MAINLINE (CONTINUOUS)
Location:
  • Town of Deerfield
  • City of Northampton
  • City of Springfield
  • Design Responsibility: Consultant
    Project Manager:
    Estimated Total Contract Cost: $1,725,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: PS&E Received (as of 05/23/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/08/2021
    Project Management
    Final Design PS&E Received 05/23/2022