Project Description:
LEOMINSTER- CULVERT REPLACEMENT, L-08-033 (6RF), MOUNT ELAM ROAD OVER MONOOSNOC BROOK
The scope of work for this project will consist of a functional replacement of the existing culvert, reconstruction of the roadway approaches, safety and other related improvements.
Location:
  • City of Leominster
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $1,190,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 03/22/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/10/2021
    Project Initiation Form PIF Entered 12/10/2021
    Project Initiation Form PRC Submitted 12/10/2021
    Project Review Committee PRC Approved 02/10/2022
    Project Management
    Consultant Contract Process NTP Issued 03/22/2023