Project Description:
WESTFIELD- INTERSECTION IMPROVEMENTS AT SOUTHAMPTON ROAD (ROUTE 10/202), SERVISTAR INDUSTRIAL WAY AND BARNES AIRPORT DRIVE
Location:
  • City of Westfield
  • Design Responsibility: Consultant
    Construction Begins: Winter 2026/2027
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $4,050,000.00
    Estimated Total Federal Participating Construction Cost: $4,350,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / (YOE $4,872,000) / 34.5 TEC / Pre 25% / STBG
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,897,600.00
    State Cost: $974,400.00
    Total Cost: $4,872,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/14/2022
    Project Need Form PNF Approved 12/16/2021
    Project Initiation Form PIF Entered 01/14/2022
    Project Initiation Form PIF Approved 01/06/2022
    Project Initiation Form PRC Submitted 01/28/2022
    Project Review Committee PRC Approved 02/10/2022