Project Description: |
BOSTON- TUNNEL PRESERVATION WITHIN MHS TUNNELS
This project will undertake various drainage improvements and preservation activities on tunnel infrastructure within the MHS Tunnels.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2025 |
Project Manager: | Hema P Bhatt |
Estimated Total Contract Cost: | $17,669,833.70 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 6 |
Current Status: | 100% Package Received (as of 04/12/2024 ) |
|
Bridges |
|
|
|