Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHBOROUGH- BELMONT STREET WATER LINE EXTENSION ON ROUTE 9
Work consists of installing water main extensions, hydrants, valves and decommissioning of existing private wells.
Location:
  • Town of Northborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $883,345.43
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: PS&E Received (as of 09/05/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/19/2022
    Project Initiation Form PIF Entered 01/19/2022
    Project Initiation Form PRC Submitted 01/26/2022
    Project Review Committee PRC Approved 02/10/2022
    Project Management
    100% Design 100% Package Received 09/09/2022
    100% Design 100% Package Received - Resub 1 11/03/2022
    75% Design 75% Package Received 05/18/2022
    Final Design PS&E Received 09/05/2023