Project Description:
WORCESTER- FLOOD RELIEF ON ROUTE 20, GRAFTON STREET (ROUTE 122) INTERCHANGE TO FLINT POND
Location:
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $5,254,719.78
    Estimated Total Federal Participating Construction Cost: $5,609,752.96
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $3,016,000, Design Status = Approved, YOE = 4%
  • Category FA - Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation (PROTECT)
    Federal Cost: $2,412,800.00
    State Cost: $603,200.00
    Total Cost: $3,016,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/20/2022
    Project Need Form PNF Approved 01/18/2022
    Project Initiation Form PIF Entered 01/20/2022
    Project Initiation Form PIF Approved 01/18/2022
    Project Initiation Form PRC Submitted 02/10/2022
    Project Review Committee PRC Approved 06/01/2023