| Project Description: |
MILTON- INTERSECTION IMPROVEMENTS AT ROUTE 138 AND BRADLEE ROAD
This project will reconstruct the 5-legged intersection at Route 138 and Bradlee Road into a roundabout.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2029 |
| Project Manager: | Aidee Cira![]() |
| Estimated Total Contract Cost: | $2,562,300.00 |
| Estimated Total Federal Participating Construction Cost: | $2,752,100.00 |
| Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
| District: | District 6 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 11/04/2022 ) |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||