COHASSET- CORRIDOR IMPROVEMENTS ON CHIEF JUSTICE CUSHING HIGHWAY (ROUTE 3A)
Location:
  • Town of Cohasset
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $8,281,531.80
    Estimated Total Federal Participating Construction Cost: $8,956,255.20
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/21/2022
    Project Need Form PNF Approved 01/11/2022
    Project Initiation Form PIF Entered 01/21/2022
    Project Initiation Form PIF Approved 01/21/2022
    Project Initiation Form PRC Submitted 01/25/2022
    Project Review Committee PRC Approved 02/10/2022