Project Description:
HARVARD- BRIDGE PRESERVATION, H-09-015, H-09-016 & H-09-017, ROUTE 2 OVER THE NASHUA RIVER, TANK ROAD, BOSTON AND MAINE RAILROAD
The scope of work for this project will consist of cleaning and painting, substructure repairs and other preservation activities for the three bridges that carry Route 2 (EB & WB) over the Nashua River, Tank Road and the BMRR in Harvard. The scope of work will also include partial demolition and alteration of the superstructure carrying Route 2 over Tank Road.
Location:
  • Town of Harvard
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2023/2024
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $3,588,439.00
    Estimated Total Federal Participating Construction Cost: $3,871,588.00
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 09/09/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: HARVARD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Increased to 3,706,048 via STIP Action 16.
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $2,964,838.40
    State Cost: $741,209.60
    Total Cost: $3,706,048.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/22/2022
    Project Initiation Form PIF Entered 01/22/2022
    Project Initiation Form PRC Submitted 01/22/2022
    Project Review Committee PRC Approved 02/10/2022
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 06/28/2023
    100% Design 100% Package Comments to DE 07/31/2023
    Final Design PS&E Received 08/11/2023
    Final Design PS&E Received - Resub 1 08/22/2023