BOSTON- BRIDGE PRESERVATION, B-16-056, CAMBRIDGE STREET OVER I-90
Project will preserve the bridge deck on Cambridge Street over I-90 in order to extend its lifespan until a future bridge replacement is performed. The work will include deck patching, substructure patching, steel beam end repairs, and joint replacement.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: John Fallon
    Estimated Total Contract Cost: $15,256,248.48
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 25% Package Received - Resub 1 (as of 08/20/2024 )

    Contracts (1) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/31/2022
    Project Need Form PNF Approved 01/26/2022
    Project Initiation Form PIF Entered 01/31/2022
    Project Initiation Form PIF Approved 01/31/2022
    Project Initiation Form PRC Submitted 01/31/2022
    Project Review Committee PRC Approved 05/31/2024
    Project Management
    25% Design 25% Package Received - Resub 1 08/20/2024
    75% Design 75% Package Received 01/20/2022
    75% Design 75% Package Received - Resub 1 08/20/2024