MIDDLEBOROUGH- CONSTRUCTION OF MODULAR OFFICES AND ASSOCIATED SITE WORK AT VINE STREET AND WEST GROVE STREET (ROUTE 28) MAINTENANCE DEPOTS
Location:
  • Town of Middleborough
  • Construction Begins: Winter 2022/2023
    Resident Engineer: Charles Young
    Construction Bid Price: $3,263,508.00
    District: District 5
    Current Status: The Buildings on Vine St and W Grove St Have been installed and come 90% completed. Finish Buttoning up The interior and exterior System. Complete The water tie in and sewer stub. All Electrical Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/01/2024)

    Contracts (1) Progress
    # 119536 -- Construction Contract
    Construction of Modular Office Buildings and Associated Site Work at the Vine Street and West Grove Street (Route 28) Maintenance Depots (612628) (Re-Advertised Project) 75% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/14/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The Buildings on Vine St and W Grove St Have been installed and come 90% completed. Finish Buttoning up The interior and exterior System. Complete The water tie in and sewer stub. All Electrical Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/03/2022
    Project Initiation Form PIF Entered 02/03/2022
    Project Initiation Form PRC Submitted 02/03/2022
    Project Review Committee PRC Approved 02/03/2022
    Project Status Advertised 03/05/2022
    Project Status Advertised 07/30/2022
    Project Management
    Final Design PS&E Received 02/08/2022
    Final Design PS&E to FAPRO 03/01/2022