Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- FLOOD PROTECTION OF CENTRAL ARTERY VENTILATION BUILDING #6 AT FID KENNEDY AVENUE (DESIGN ONLY)
This project will identify, design, and procure flood protections in various forms as needed at the following MassDOT facilities: 19 Fid Kennedy Avenue, 145 Havre Street, 50 Massport Haul Road, 370 D Street, and 250 Frontage Road.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Mark Carmichael
    Estimated Total Contract Cost: $216,502.50
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 73478 -- Design -- Bridge Open End
    Work will consist of inspection of MassDOT owned Dams and Spillway structures and the design of repairs and/or rehabilitation of the dams and spillway structures. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/08/2022
    Project Need Form PNF Approved 01/26/2022
    Project Initiation Form PIF Entered 02/08/2022
    Project Initiation Form PIF Approved 01/26/2022
    Project Initiation Form PRC Submitted 02/08/2022
    Project Review Committee PRC Approved 02/10/2022
    Project Management