CHELMSFORD- LOWELL- BRIDGE REPLACEMENT, C-08-039, GORHAM STREET (ST 3A) OVER I-495 AND C-08-036, WESTFORD STREET OVER I-495 (DB)
Location:
  • Town of Chelmsford
  • City of Lowell
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Aleksey N Belov
    Estimated Total Contract Cost: $39,455,020.25
    Estimated Total Federal Participating Construction Cost: $42,127,191.99
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 02/03/2024 )

    Contracts (1) Progress
    # 115768 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: CHELMSFORD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Total cost: $44,358,906; Funding: NGBP; TEC: 5.57 out of 18
  • Category FA - Next Generation Bridge GANs
    Federal Cost: $35,487,124.80
    State Cost: $8,871,781.20
    Total Cost: $44,358,906.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/09/2022
    Project Initiation Form PIF Entered 02/09/2022
    Project Initiation Form PRC Submitted 02/09/2022
    Project Review Committee PRC Approved 02/10/2022
    Project Status Advertised 02/03/2024
    Project Management
    100% Design 100% Package Received 01/02/2024
    100% Design 100% Package Received 01/22/2024
    100% Design 100% Package Comments to DE 11/20/2023
    25% Design 25% Package Received 12/23/2022
    25% Design 25% Package Comments to DE 02/27/2023
    25% Design 25% Package Received - Resub 1 08/15/2023
    25% Design Design Public Hearing 06/14/2023