Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHELMSFORD- LOWELL- BRIDGE REPLACEMENT, C-08-039, GORHAM STREET (ST 3A) OVER I-495 AND C-08-036, WESTFORD STREET OVER I-495 (DB)
Location:
  • Town of Chelmsford
  • City of Lowell
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Aleksey N Belov
    Estimated Total Contract Cost: $39,455,020.25
    Estimated Total Federal Participating Construction Cost: $42,127,191.99
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 02/03/2024 )

    Contracts (1) Progress
    # 115768 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/09/2022
    Project Initiation Form PIF Entered 02/09/2022
    Project Initiation Form PRC Submitted 02/09/2022
    Project Review Committee PRC Approved 02/10/2022
    Project Status Advertised 02/03/2024
    Project Management
    100% Design 100% Package Received 01/02/2024
    100% Design 100% Package Received 01/22/2024
    100% Design 100% Package Comments to DE 11/20/2023
    25% Design 25% Package Received 12/23/2022
    25% Design 25% Package Comments to DE 02/27/2023
    25% Design 25% Package Received - Resub 1 08/15/2023
    25% Design Design Public Hearing 06/14/2023
    Final Design PS&E to FAPRO 01/23/2024