DISTRICT 6- SCHEDULED & EMERGENCY STRUCTURAL & SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
Location:
Construction Begins: Autumn 2022
Resident Engineer: John Wagner
Construction Bid Price: $3,316,045.00
District: District 6

Contracts (1) Progress
# 120460 -- Construction Contract
Scheduled and Emergency Bridge Structural and Substructure Repairs at Various Locations 24% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/25/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/17/2022
    Project Need Form PNF Approved 02/17/2022
    Project Initiation Form PIF Entered 02/17/2022
    Project Initiation Form PIF Approved 02/17/2022
    Project Initiation Form PRC Submitted 02/17/2022
    Project Review Committee PRC Approved 02/18/2022
    Project Status Advertised 10/08/2022
    Project Management
    100% Design 100% Package Received 08/03/2022
    100% Design 100% Package Comments to DE 09/01/2022
    Final Design PS&E Received 09/09/2022
    Final Design PS&E to FAPRO 09/30/2022