WEBSTER- OXFORD- AUBURN- GUIDE AND TRAFFIC SIGN REPLACEMENT ON I-395
This project is for the replacement and upgrading of guide and traffic signs along Interstate 395 and intersecting secondary roadways between the Connecticut/Massachusetts state line in Webster and the US 20 interchange in Auburn, including applicable signing on intersecting secondary roadways
Location:
  • Town of Auburn
  • Town of Oxford
  • Town of Webster
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $393,360.00
    Estimated Total Federal Participating Construction Cost: $447,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: AUBURN
    OXFORD
    WEBSTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $464,880, Design Status = Approved, YOE = 4%
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $418,392.00
    State Cost: $46,488.00
    Total Cost: $464,880.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2022
    Project Initiation Form PIF Entered 02/24/2022
    Project Initiation Form PRC Submitted 02/24/2022
    Project Review Committee PRC Approved 02/28/2022
    Project Management