Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- BRIDGE PRESERVATION, W-44-111, W-44-113, W-44-114, I -290 (EB/WB) OVER LINCOLN STREET, COLBY AVENUE AND PLANTATION STREET
Location:
  • City of Worcester
  • Construction Begins: Spring 2023
    Resident Engineer: Kevin Troy
    Construction Bid Price: $3,789,000.00
    District: District 3

    Contracts (1) Progress
    # 121540 -- Construction Contract
    Bridge Cleaning, Painting and Repairs Br. Nos. W-44-111, W-44-113 & W-44-114 on Interstate 290 10% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/11/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2022
    Project Initiation Form PIF Entered 02/24/2022
    Project Initiation Form PRC Submitted 02/24/2022
    Project Review Committee PRC Approved 03/02/2022
    Project Status Advertised 03/04/2023
    Project Management
    100% Design 100% Package Received 08/30/2022
    100% Design 100% Package Comments to DE 11/02/2022
    Final Design PS&E Received 11/10/2022
    Final Design PS&E Received - Resub 1 01/17/2023