Project Description:
DISTRICT 5- DRAWBRIDGE OPERATION, REPAIR AND SYSTEMATIC PRESERVATION AT VARIOUS LOCATIONS (INCLUDING MARTHA'S VINEYARD)
Location:
Construction Begins: Autumn 2022
Resident Engineer: Louis daPonte
Construction Bid Price: $4,251,905.00
District: District 5

Contracts (1) Progress
# 120461 -- Construction Contract
Scheduled and Emergency Drawbridge Operation and Repairs at Various Locations (Including Martha's Vineyard) 52% Complete

Bridges

Contract Dates
Notice to Proceed: 12/08/2022
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 02/25/2022
Project Need Form PNF Approved 02/25/2022
Project Initiation Form PIF Entered 02/25/2022
Project Initiation Form PIF Approved 02/25/2022
Project Initiation Form PRC Submitted 03/01/2022
Project Review Committee PRC Approved 03/02/2022
Project Status Advertised 10/08/2022
Project Management
100% Design 100% Package Received 06/17/2022
100% Design 100% Package Comments to DE 07/25/2022
Final Design PS&E Received 08/08/2022
Final Design PS&E Received - Resub 1 09/09/2022