Project Description:
TEWKSBURY- BRIDGE PRESERVATION OF T-03-014, I-495 OVER ROUTE 133, AND T-03-015, I-495 OVER ROUTE 38
Location:
  • Town of Tewksbury
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2023
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $4,730,000.00
    Estimated Total Federal Participating Construction Cost: $5,160,000.00
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2022
    Project Need Form PNF Approved 03/02/2022
    Project Initiation Form PIF Entered 03/02/2022
    Project Initiation Form PIF Approved 03/02/2022
    Project Initiation Form PRC Submitted 03/02/2022
    Project Review Committee PRC Approved 03/02/2022
    Project Management