TEWKSBURY- BRIDGE PRESERVATION OF T-03-014, I-495 OVER ROUTE 133, AND T-03-015, I-495 OVER ROUTE 38
This project will consist of concrete patching, steel cleaning and painting, and bearing replacement of bridge in Tewksbury.
Location:
  • Town of Tewksbury
  • Construction Begins: Summer 2023
    Resident Engineer: Ahmad Rafieizadeh
    Construction Bid Price: $7,310,356.00
    District: District 4

    Contracts (2) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 122517 -- Construction Contract
    Bridge Preservation of T-03-014, I-495 over Route 133, and T-03-015, I-495 over Route 38 41% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 09/12/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2022
    Project Need Form PNF Approved 03/02/2022
    Project Initiation Form PIF Entered 03/02/2022
    Project Initiation Form PIF Approved 03/02/2022
    Project Initiation Form PRC Submitted 03/02/2022
    Project Review Committee PRC Approved 03/02/2022
    Project Status Advertised 06/17/2023
    Project Management
    75% Design 75% Package Received 02/02/2023
    75% Design 75% Package Comments to DE 03/21/2023
    Final Design PS&E Received 04/27/2023
    Final Design PS&E Received - Resub 1 05/19/2023
    Final Design PS&E Received - Resub 2 05/31/2023