Project Description:
BOSTON- TUNNEL LIGHTING REPLACEMENT ON I-90 EB & WB (CRC 17H & CRC 17I)
Project includes the I-90 tunnel system between the Prudential Tunnel and the Ted Williams Tunnel. The roadways included are I-90 WB, I-90 EB, I-90 HOV, Ramps B, D, DN, W-SS, A, C, F, I, L & L-CS. All existing luminaries, wiring will be removed & installing new LED lighting, raceways, junction boxes.
Location:
  • City of Boston
  • Construction Begins: Autumn 2023
    Resident Engineer: Le Truong
    Construction Bid Price: $88,744,788.00
    District: District 6

    Contracts (2) Progress
    # 122343 -- Construction Contract
    Tunnel Lighting Replacement on I-90 EB & WB (CRC 17H & CRC 17I) 31% Complete
    # 60493 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering for various projects

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/05/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2022
    Project Need Form PNF Approved 03/28/2022
    Project Initiation Form PIF Entered 03/28/2022
    Project Initiation Form PIF Approved 03/28/2022
    Project Initiation Form PRC Submitted 03/28/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Status Advertised 06/03/2023
    Project Management
    Final Design PS&E Received 06/30/2022
    Final Design PS&E to Peer Reviewer 12/05/2022
    Final Design Peer Review Comments to DE 01/31/2023
    Final Design PS&E Received - Resub 1 04/18/2023
    Final Design PS&E Received - Resub 2 05/11/2023