Project Description:
WILLIAMSTOWN- ROUTE 7 ACCESS IMPROVEMENTS AT MOUNT GREYLOCK REGIONAL SCHOOL
To address access and egress concerns at this location, the District is proposing minor geometric improvements consisting of traffic island modification, changes to auxiliary turn lanes, highway resurfacing, and revised pavement markings to re-assign motor vehicle lanes and bicycle accommodation. An Intersection Collision Warning System (ICWS) will also be installed on Route 7 in advance of the school entrance. These changes are being proposed in response to operational and safety concerns by parents and school officials regarding traffic conditions at the school entrance during arrival and dismissal times.
Location:
  • Town of Williamstown
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $540,000.00
    Estimated Total Federal Participating Construction Cost: $600,000.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: WILLIAMSTOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total Project Cost = $520,000; YOE = 4%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $416,000.00
    State Cost: $104,000.00
    Total Cost: $520,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/31/2022
    Project Need Form PNF Approved 03/31/2022
    Project Initiation Form PIF Entered 03/31/2022
    Project Initiation Form PIF Approved 03/31/2022
    Project Initiation Form PRC Submitted 04/15/2022
    Project Review Committee PRC Approved 04/15/2022
    Project Management