HARVARD- LITTLETON- RESURFACING AND RELATED WORK ON ROUTE 2, FROM OLD LITTLETON ROAD BRIDGE TO EAST OF WHITCOMB AVENUE BRIDGE
The proposed project extends along Route 2, from the Old Littleton Road bridge in Harvard to east of the Whitcomb Avenue bridge in Littleton, for a distance of about 2,400 feet. The project consists of a reclamation of the roadway pavement to correct the super elevation along the curve, installation of a new median barrier and drainage improvements. Related work includes installation of MASH compliant guard rail, upgraded signage and pavement markings.
Location:
  • Town of Harvard
  • Town of Littleton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $5,206,250.00
    Estimated Total Federal Participating Construction Cost: $5,631,250.00
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/14/2022
    Project Need Form PNF Approved 04/11/2022
    Project Initiation Form PIF Entered 04/14/2022
    Project Initiation Form PIF Approved 04/13/2022
    Project Initiation Form PRC Submitted 04/29/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management