MIDDLEBOROUGH- BRIDGE PRESERVATION, M-18-017 (463), I-495 OVER ROUTE 105 & MBTA/MACRR
The bridge preservation project will determine the source of water washing out the slope and make repairs in the Town of Middleborough.
Location:
  • Town of Middleborough
  • Construction Begins: Autumn 2023
    Resident Engineer: Michael Horton
    Construction Bid Price: $3,072,941.00
    District: District 5

    Contracts (1) Progress
    # 124099 -- Construction Contract
    Bridge Preservation, M-18-017 (463), I-495 over Route 105 & MBTA/MACRR

    Bridges

    Contract Dates
    Notice to Proceed: 12/01/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/21/2022
    Project Initiation Form PIF Approved 04/21/2022
    Project Initiation Form PRC Submitted 04/21/2022
    Project Review Committee PRC Approved 04/25/2022
    Project Status Advertised 09/16/2023
    Project Management
    100% Design 100% Package Received 07/16/2023
    100% Design 100% Package Comments to DE 08/01/2023
    Final Design PS&E Received 08/14/2023
    Final Design PS&E Received - Resub 1 08/30/2023