MIDDLEBOROUGH- BRIDGE PRESERVATION, M-18-017 (463), I-495 OVER ROUTE 105 & MBTA/MACRR
The bridge preservation project will determine the source of water washing out the slope and make repairs in the Town of Middleborough.
Location:
  • Town of Middleborough
  • Construction Begins: Autumn 2023
    Resident Engineer: Michael Horton
    Construction Bid Price: $3,072,941.00
    District: District 5
    Current Status: - Atsalis Brothers Painting has completed blasting and priming operations on spans 1-3, 3A and 4A. MIG will conduct substructure concrete pours on the East and West retaining wall sections/columns requiring various lane closures on Rt.105 from 8PM to 4AM. Normal work hours are Monday through Saturday, 6:00 AM to 4:30 PM (as of 03/02/2026)
    Additional Info: Atsalis continues to work with the MBTA & Keolis to provide flagging services for all operations. (as of 03/02/2026)

    Contracts (1) Progress
    # 124099 -- Construction Contract
    Bridge Preservation, M-18-017 (463), I-495 over Route 105 & MBTA/MACRR Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/01/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/21/2022
    Project Initiation Form PIF Approved 04/21/2022
    Project Initiation Form PRC Submitted 04/21/2022
    Project Review Committee PRC Approved 04/25/2022
    Project Status Advertised 09/16/2023
    Project Management
    100% Design 100% Package Received 07/16/2023
    100% Design 100% Package Comments to DE 08/01/2023
    Final Design PS&E Received 08/14/2023
    Final Design PS&E Received - Resub 1 08/30/2023