Project Description: |
MIDDLEBOROUGH- BRIDGE PRESERVATION, M-18-017 (463), I-495 OVER ROUTE 105 & MBTA/MACRR
The bridge preservation project will determine the source of water washing out the slope and make repairs in the Town of Middleborough.
|
Location: |
|
Construction Begins: | Autumn 2023 |
Resident Engineer: | Michael Horton![]() |
Construction Bid Price: | $3,072,941.00 |
District: | District 5 |
Current Status: | - Atsalis Brothers Painting is nearing completion of the quick-decking installation at the bridge location. Upon completion over the next few weeks, Atsalis will look to begin Blast & Prime Operations. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 09/22/2025) |
Additional Info: | Atsalis continues to work with the MBTA & Keolis flagging to construct containment over the railroad tracks and mobilize the proper equipment for bridge painting operations. (as of 09/22/2025) |
|