Project Description: |
MIDDLEBOROUGH- BRIDGE PRESERVATION, M-18-017 (463), I-495 OVER ROUTE 105 & MBTA/MACRR
The bridge preservation project will determine the source of water washing out the slope and make repairs in the Town of Middleborough.
|
Location: |
|
Construction Begins: | Autumn 2023 |
Resident Engineer: | Michael Horton![]() |
Construction Bid Price: | $3,072,941.00 |
District: | District 5 |
Current Status: | - Physical work is scheduled to begin 3/17/25 - Atsalis Brothers cleared & prepared a laydown area to begin physical work operations. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 03/28/2025) |
Additional Info: | Atsalis will work with Keolis flagging to access the bridge in and around the railroad tracks. No immediate impacts to traffic on Rt-105 or I-1495. (as of 03/28/2025) |
|
Bridges
|
|
|
|
|