| Project Description: |
MIDDLEBOROUGH- BRIDGE PRESERVATION, M-18-017 (463), I-495 OVER ROUTE 105 & MBTA/MACRR
The bridge preservation project will determine the source of water washing out the slope and make repairs in the Town of Middleborough.
|
| Location: |
|
| Construction Begins: | Autumn 2023 |
| Resident Engineer: | Michael Horton![]() |
| Construction Bid Price: | $3,072,941.00 |
| District: | District 5 |
| Current Status: | - Atsalis Brothers Painting are mostly complete with Finish Coat Application on all spans. - MIG will begin beam end repairs & other bridge repairs from I-495: To be scheduled (night shifts) Normal work hours are Monday through Saturday, 7:00 AM to 5:30 PM (as of 06/03/2026) |
| Additional Info: | Atsalis & MIG continue to work with the MBTA & Keolis to provide flagging services for all operations. (as of 06/03/2026) |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||