Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- CLEANING AT BRIDGE LOCATIONS ALONG THE I-495 CORRIDOR
Location:
Construction Begins: Winter 2023/2024
Resident Engineer: Michael Horton
Construction Bid Price: $1,615,370.00
District: District 5
Current Status: - All punchlist work has been completed. - Project Finals underway. (as of 05/07/2026)

Contracts (1) Progress
# 124846 -- Construction Contract
Cleaning at Bridge Locations along the I-495 Corridor Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/22/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    - All punchlist work has been completed. - Project Finals underway.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/21/2022
    Project Initiation Form PIF Approved 04/21/2022
    Project Initiation Form PRC Submitted 04/21/2022
    Project Review Committee PRC Approved 04/25/2022
    Project Status Advertised 12/16/2023
    Project Management
    100% Design 100% Package Received 09/01/2023
    100% Design 100% Package Comments to DE 09/26/2023
    Final Design PS&E Received 10/10/2023
    Final Design PS&E to FAPRO 11/29/2023