Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY VEGETATION MANAGEMENT (MECHANICAL) AT VARIOUS LOCATIONS
Location:
Construction Begins: Winter 2022/2023
Resident Engineer: Cory Alemian
Construction Bid Price: $990,795.00
District: District 6

Contracts (1) Progress
# 120984 -- Construction Contract
Scheduled and Emergency Vegetation Management (Mechanical) at Various Locations 97% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/08/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/21/2022
    Project Initiation Form PIF Approved 04/21/2022
    Project Initiation Form PRC Submitted 04/21/2022
    Project Review Committee PRC Approved 04/26/2022
    Project Status Advertised 12/17/2022
    Project Management
    100% Design 100% Package Received 10/17/2022
    Final Design PS&E Received 11/16/2022
    Final Design PS&E to FAPRO 11/18/2022