Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BUCKLAND- RECONSTRUCTION OF UPPER NORTH STREET
Project will include about 0.45-mile of highway reconstruction with minor widening to achieve complete streets compliance. The town wants to see continuous sidewalk along the project length, to complete a walkable and bikeable connection from the village of Shelburne Falls to Route 112. In a future project (607610) MassDOT will construct buffered bike-lanes on Route 112 from North Street to the Buckland Recreation Area, about 1.2-miles to the west.
Location:
  • Town of Buckland
  • Construction Begins: Autumn 2023
    Resident Engineer: John Tietgens
    Construction Bid Price: $2,710,007.00
    District: District 1

    Contracts (2) Progress
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 124021 -- Construction Contract
    Reconstruction of Upper North Street 4% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/12/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/25/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/25/2022
    Project Initiation Form PIF Approved 04/25/2022
    Project Initiation Form PRC Submitted 04/29/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 04/04/2023
    25% Design 25% Package Received 01/27/2023
    25% Design Design Public Hearing 03/23/2023
    75% Design 75% Package Received 04/04/2023
    Final Design PS&E Received 07/17/2023
    Final Design PS&E to FAPRO 08/25/2023
    Final Design PS&E Received - Resub 1 08/07/2023