BARNSTABLE- CORRIDOR IMPROVEMENTS ON ROUTE 28, FROM LINCOLN STREET TO GARDEN LANE
Work on this project will consist of traffic signal reconstruction at Pitchers Way and improvements at the Lincoln Road/Lincoln Road Ext intersections to address safety concerns at both intersections. Roadway improvements, multi modal accommodations, signage and striping will be included as part of this project.
Location:
  • Town of Barnstable
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $9,709,000.00
    Estimated Total Federal Participating Construction Cost: $10,414,775.00
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/27/2022
    Project Need Form PNF Approved 04/20/2022
    Project Initiation Form PIF Entered 04/27/2022
    Project Initiation Form PIF Approved 04/27/2022
    Project Initiation Form PRC Submitted 04/29/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management