Project Description:
WINCHENDON- INTERSECTION IMPROVEMENTS AT BLAIR SQUARE: FRONT STREET, CENTRAL STREET AND SPRING STREET AND ROUTES 12 AND 202
The primary project goals include implementation of improvements to improve traffic operations and enhance safety and accessibility for all users (motor vehicles, pedestrians, and bicycles) by reducing conflict areas, minimizing pedestrian crossing distances and providing facilities for bicycles. The intersection currently experiences safety and operational concerns, including high crash rates, side street vehicular delays, limited sight distances, driver confusion due to unconventional vehicular traffic control, insufficient pedestrian accommodations, and lack of bicycle accommodations.
Location:
  • Town of Winchendon
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2029
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $4,126,995.88
    Estimated Total Federal Participating Construction Cost: $4,479,401.13
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Comments to DE (as of 07/09/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: WINCHENDON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,788,164.80
    State Cost: $947,041.20
    Total Cost: $4,735,206.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/27/2022
    Project Need Form PNF Approved 04/01/2022
    Project Initiation Form PIF Entered 04/27/2022
    Project Initiation Form PIF Approved 04/20/2022
    Project Initiation Form PRC Submitted 05/03/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management
    25% Design 25% Package Received 04/04/2024
    25% Design 25% Package Comments to DE 07/09/2024