Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
EASTHAMPTON- MOUNTAIN VIEW SCHOOL IMPROVEMENTS (SRTS)
The project includes constructing a 400 foot long accessible multiuse path connection from the existing Manhan Rail Trail bike path to Park Street, construction of a 3600 foot long, eight foot wide sidepath along Park Street to the entrance of the existing White Brook Middle and future Mountain View Pk-8 School, new ADA ramps and crosswalks at 4 street crossings (at Ward Avenue, Garfield Avenue, Bryan Avenue, and Taft Avenue), new ADA ramps at 19 driveways, and the narrowing of 1300 feet of Park Street through new pavement markings for traffic calming and to accommodate the sidepath.
Location:
  • Town of Easthampton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Alolade O Campbell
    Estimated Total Contract Cost: $1,521,311.60
    Estimated Total Federal Participating Construction Cost: $1,647,780.60
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: EASTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,423,682.40
    State Cost: $355,920.60
    Total Cost: $1,779,603.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/27/2022
    Project Need Form PNF Approved 03/17/2022
    Project Initiation Form PIF Entered 04/27/2022
    Project Initiation Form PIF Approved 04/22/2022
    Project Initiation Form PRC Submitted 05/03/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management