SOUTHAMPTON- REHABILITATION/RECONSTRUCTION & RELATED WORK ON EAST STREET, FROM COLLEGE HIGHWAY (ROUTE 10) TO WHISPERING MEADOW LANE
The project proposes to construct two 11 foot wide travel lanes with 2 foot wide shoulders. A 10 foot wide shared use path and wetlands buffer is proposed for the entire South East Street along with a 5 foot wide sidewalk. A variable buffer is also proposed on the north side to 570 feet east of Clark Street to preserved trees.
Location:
  • Town of Southampton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2028
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $8,877,525.50
    Estimated Total Federal Participating Construction Cost: $9,352,769.38
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/28/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/28/2022
    Project Initiation Form PIF Approved 04/27/2022
    Project Initiation Form PRC Submitted 05/03/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management