Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOUTHAMPTON- REHABILITATION/RECONSTRUCTION & RELATED WORK ON EAST STREET, FROM COLLEGE HIGHWAY (ROUTE 10) TO WHISPERING MEADOW LANE
The project proposes to construct two 11 foot wide travel lanes with 2 foot wide shoulders. A 10 foot wide shared use path and wetlands buffer is proposed for the entire South East Street along with a 5 foot wide sidewalk. A variable buffer is also proposed on the north side to 570 feet east of Clark Street to preserved trees.
Location:
  • Town of Southampton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2028
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $8,877,525.50
    Estimated Total Federal Participating Construction Cost: $9,352,769.38
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SOUTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $10,475,101 STBG / 38 TEC / Pre 25$
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,380,080.80
    State Cost: $2,095,020.20
    Total Cost: $10,475,101.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/28/2022
    Project Need Form PNF Approved 04/21/2022
    Project Initiation Form PIF Entered 04/28/2022
    Project Initiation Form PIF Approved 04/27/2022
    Project Initiation Form PRC Submitted 05/03/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management