Project Description:
GREENFIELD- MONTAGUE- BRIDGE REPLACEMENT, G-12-002, TURNERS FALLS ROAD OVER CONNECTICUT RIVER, M-28-015, 5TH STREET OVER CANAL, M-28-16A, 6TH STREET OVER CANAL
Location:
  • Town of Greenfield
  • Town of Montague
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Courtney Sulerud
    Estimated Total Contract Cost: $54,048,466.17
    Estimated Total Federal Participating Construction Cost: $56,050,261.22
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 11/21/2022 )

    Contracts (1) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: GREENFIELD
    MONTAGUE
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $48,427,425.60
    State Cost: $12,106,856.40
    Total Cost: $60,534,282.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/03/2022
    Project Need Form PNF Approved 05/02/2022
    Project Initiation Form PIF Entered 05/03/2022
    Project Initiation Form PIF Approved 05/02/2022
    Project Initiation Form PRC Submitted 05/04/2022
    Project Review Committee PRC Approved 05/12/2022
    Project Management
    Consultant Contract Process NTP Issued 11/21/2022