Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY CLEANING OF DRAINAGE STRUCTURES AND PIPES AT VARIOUS LOCATIONS
Location:
Construction Begins: Autumn 2023
Resident Engineer: Cory Alemian
Construction Bid Price: $425,871.00
District: District 6

Contracts (1) Progress
# 123879 -- Construction Contract
Scheduled & Emergency Cleaning of Drainage Structures and Pipes at Various Locations

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/31/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/31/2022
    Project Need Form PNF Approved 05/31/2022
    Project Initiation Form PIF Entered 05/31/2022
    Project Initiation Form PIF Approved 05/31/2022
    Project Initiation Form PRC Submitted 05/31/2022
    Project Review Committee PRC Approved 08/30/2022
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 06/21/2023
    Final Design PS&E Received 07/11/2023
    Final Design PS&E to FAPRO 07/20/2023