Project Description:
BEVERLY- SALEM- BRIDGE PRESERVATION, B-11-005=S-01-013 (307 & 308), KERNWOOD AVENUE OVER THE DANVERS RIVER
Location:
  • City of Beverly
  • City of Salem
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $7,347,527.60
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 03/02/2024 )

    Contracts (1) Progress
    # 115768 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/01/2022
    Project Initiation Form PIF Entered 06/01/2022
    Project Initiation Form PRC Submitted 06/01/2022
    Project Review Committee PRC Approved 06/06/2022
    Project Status Advertised 03/02/2024
    Project Management
    100% Design 100% Package Received 07/07/2023
    100% Design 100% Package Comments to DE 08/16/2023
    100% Design 100% Package Received - Resub 1 09/14/2023
    Final Design PS&E Received 11/09/2023
    Final Design PS&E Received - Resub 1 12/12/2023
    Final Design PS&E Received - Resub 2 01/05/2024