| Project Description: |
DISTRICT 4- SCHEDULED & EMERGENCY BRIDGE STRUCTURAL REPAIRS (INCLUDING PAINTING) AT VARIOUS LOCATIONS
This project shall repair or replace the deteriorated bridge elements of any structure under the control of District 4. Work shall include superstructure, railing, deck, joints, sidewalk and scupper repairs. emergency removal of concrete and reinforcing steel bridges will also be performed if necessary.
|
| Location: | |
| Construction Begins: | Autumn 2023 |
| Resident Engineer: | Andrew Leahy![]() |
| Construction Bid Price: | $2,134,725.00 |
| District: | District 4 |
|