Project Description:
FRAMINGHAM- BRIDGE PRESERVATION, F-07-050, STATE ROUTE 9 OVER I-90
The scope of this project will consist of maintenance and preservation work that will include deck repair, new wearing surface, cleaning and painting structural steel for the bridge that carries State 9 over I-90. It will also include repairs to bearing and substructure and other related maintenance work.
Location:
  • Town of Framingham
  • Construction Begins: Autumn 2022
    Resident Engineer: Alexa Weeden
    Construction Bid Price: $4,246,680.00
    District: District 3

    Contracts (1) Progress
    # 120571 -- Construction Contract
    Bridge Repairs and Related Work (Including Painting) Br. No. F-07-050 (Steel) Route 9 over Interstate 90

    Bridges

    Contract Dates
    Notice to Proceed: 12/12/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2022
    Project Initiation Form PIF Entered 06/08/2022
    Project Initiation Form PRC Submitted 06/08/2022
    Project Review Committee PRC Approved 06/13/2022
    Project Status Advertised 10/22/2022
    Project Management
    100% Design 100% Package Received 07/01/2022
    100% Design 100% Package Comments to DE 08/09/2022
    Final Design PS&E Received 08/24/2022
    Final Design PS&E Received - Resub 1 09/20/2022