Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FALL RIVER- SOMERSET- FENDER SYSTEM REPAIRS, F-02-058=S-16-008, I-195 OVER THE TAUNTON RIVER (BRAGA BRIDGE)
Work shall consist of designing and installing new fender system elements to replace the existing damaged or missing fenders.
Location:
  • City of Fall River
  • Town of Somerset
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2024/2025
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $6,050,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: 75% Package Comments to DE (as of 03/20/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/15/2022
    Project Need Form PNF Approved 06/15/2022
    Project Initiation Form PIF Entered 06/15/2022
    Project Initiation Form PIF Approved 06/15/2022
    Project Initiation Form PRC Submitted 06/15/2022
    Project Review Committee PRC Approved 06/16/2022
    Project Management
    75% Design 75% Package Received 02/16/2024
    75% Design 75% Package Comments to DE 03/20/2024