Project Description:
FALL RIVER- SOMERSET- FENDER SYSTEM REPAIRS, F-02-058=S-16-008, I-195 OVER THE TAUNTON RIVER (BRAGA BRIDGE)
Work shall consist of designing and installing new fender system elements to replace the existing damaged or missing fenders.
Location:
  • City of Fall River
  • Town of Somerset
  • Construction Begins: Spring 2025
    Resident Engineer: Nuno Redondo
    Construction Bid Price: $9,297,770.00
    District: District 5
    Current Status: Contractors working on their submittals/schedules. Contractor delivering/storing materials on site. Contractor driving piles. Contactor to begin assembling/installing walers. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Scheduled work hours are Monday through Friday, 7:00AM to 3:00PM. Scheduled work hours are Monday through Friday, 7:00AM to 3:00PM. (as of 11/04/2026)

    Contracts (1) Progress
    # 129646 -- Construction Contract
    Fender System Repairs, F-02-058=S-16-008, I-195 over the Taunton River (Braga Bridge)

    Bridges

    Contract Dates
    Notice to Proceed: 06/18/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractors working on their submittals/schedules. Contractor delivering/storing materials on site. Contractor driving piles. Contactor to begin assembling/installing walers. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Scheduled work hours are Monday through Friday, 7:00AM to 3:00PM. Scheduled work hours are Monday through Friday, 7:00AM to 3:00PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/15/2022
    Project Need Form PNF Approved 06/15/2022
    Project Initiation Form PIF Entered 06/15/2022
    Project Initiation Form PIF Approved 06/15/2022
    Project Initiation Form PRC Submitted 06/15/2022
    Project Review Committee PRC Approved 06/16/2022
    Project Status Advertised 03/08/2025
    Project Management
    100% Design 100% Package Received 05/16/2024
    100% Design 100% Package Comments to DE 06/07/2024
    100% Design 100% Package Received - Resub 1 06/28/2024
    75% Design 75% Package Received 02/16/2024
    75% Design 75% Package Comments to DE 03/20/2024
    Final Design PS&E Received 08/09/2024
    Final Design PS&E Received - Resub 1 01/30/2025