HARVARD- LANCASTER- BRIDGE REPLACEMENT, H-09-019=L-02-020, JACKSON ROAD OVER NASHUA RIVER
.
Location:
  • Town of Harvard
  • Town of Lancaster
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: William F Brown
    Estimated Total Contract Cost: $18,432,249.30
    Estimated Total Federal Participating Construction Cost: $19,083,725.20
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Comments to DE (as of 11/01/2024 )

    Contracts (1) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: HARVARD
    LANCASTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $8,670,680.80
    State Cost: $2,167,670.20
    Total Cost: $10,838,351.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/17/2022
    Project Initiation Form PIF Entered 06/17/2022
    Project Initiation Form PRC Submitted 09/29/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    25% Design 25% Package Received 09/27/2024
    25% Design 25% Package Comments to DE 11/01/2024
    Consultant Contract Process Scope to DE 09/21/2022
    Consultant Contract Process NTP Issued 02/15/2023