Project Description:
FITCHBURG- IMPROVEMENTS AT MEMORIAL MIDDLE SCHOOL (SRTS)
The project will increase the safety and number of students walking to and from Memorial Middle School. The improvements will focus on three heavily trafficked routes to and from the school. The project bounds include: Pratt Road from the Parkhill Park parking lot to Causeway Street; Rollstone Street from Franklin Road to Pine Street, and Causeway Street between Pratt Road and Rollstone Street. All three routes connect Memorial Middle School (within an Environmental Justice area) with other Environmental Justice census tracts and will create enhancements to improve accessibility for students and other residents of these neighborhoods.
Location:
  • City of Fitchburg
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2026
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $1,864,444.50
    Estimated Total Federal Participating Construction Cost: $2,002,551.50
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 04/10/2023 )

    Contracts (3) Progress
    # 115778 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: FITCHBURG
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,666,123.20
    State Cost: $416,530.80
    Total Cost: $2,082,654.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/28/2022
    Project Need Form PNF Approved 06/17/2022
    Project Initiation Form PIF Entered 06/28/2022
    Project Initiation Form PIF Approved 06/21/2022
    Project Initiation Form PRC Submitted 06/28/2022
    Project Review Committee PRC Approved 07/08/2022
    Project Management
    Consultant Contract Process NTP Issued 04/10/2023