OAK BLUFFS- CULVERT REPLACEMENT ON BEACH ROAD AT FARM POND
The purpose and need of this project is multi-fold. The intent is address lack of adequate tidal flushing of Farm Pond due to the culvert size constraint; improve resiliency for state highway, which currently overtops in significant storm events; and improve the crossing for non-motorized traffic at the existing crosswalk; review the gap between the end of sidewalk and the beginning of the shared use path.
Location:
  • Town of Oak Bluffs
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $4,980,375.00
    Estimated Total Federal Participating Construction Cost: $5,367,688.75
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/18/2022
    Project Need Form PNF Approved 08/18/2022
    Project Initiation Form PIF Entered 08/18/2022
    Project Initiation Form PIF Approved 08/18/2022
    Project Initiation Form PRC Submitted 08/23/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Management