Project Description: |
OAK BLUFFS- CULVERT REPLACEMENT ON BEACH ROAD AT FARM POND
The purpose and need of this project is multi-fold. The intent is address lack of adequate tidal flushing of
Farm Pond due to the culvert size constraint; improve resiliency for state highway, which currently
overtops in significant storm events; and improve the crossing for non-motorized traffic at the existing
crosswalk; review the gap between the end of sidewalk and the beginning of the shared use path.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2028 |
Project Manager: | Thomas H Currier |
Estimated Total Contract Cost: | $4,980,375.00 |
Estimated Total Federal Participating Construction Cost: | $5,367,688.75 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Martha's Vineyard Commission. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|