Project Description:
CHELMSFORD- VINAL SQUARE SAFETY IMPROVEMENTS
Location:
  • Town of Chelmsford
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2028
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $6,588,170.60
    Estimated Total Federal Participating Construction Cost: $7,200,556.57
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: CHELMSFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,164,201.60
    State Cost: $1,291,050.40
    Total Cost: $6,455,252.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/22/2022
    Project Need Form PNF Approved 05/16/2022
    Project Initiation Form PIF Entered 08/22/2022
    Project Initiation Form PIF Approved 08/22/2022
    Project Initiation Form PRC Submitted 08/22/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Management