BARNSTABLE- PEDESTRIAN IMPROVEMENTS ON ROUTE 6A, FROM ROUTE 132 TO OLD JAIL LANE
There is a lack of connectivity for compliant sidewalks along the Route 6A corridor. This is a route to Barnstable Village, a school exists on this corridor and it is a residential neighborhood. Approval of this project is intended for preliminary design. Survey and preliminary design will establish the feasibility and priorities of reconstruction/installation of sidewalk along this section of Route 6A.
Location:
  • Town of Barnstable
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $4,158,000.00
    Estimated Total Federal Participating Construction Cost: $4,584,650.00
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/22/2022
    Project Need Form PNF Approved 08/18/2022
    Project Initiation Form PIF Entered 08/22/2022
    Project Initiation Form PIF Approved 08/22/2022
    Project Initiation Form PRC Submitted 08/23/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Management