Project Description:
ERVING- BRIDGE REPLACEMENT, E-10-011, CHURCH STREET OVER KEYUP BROOK
The intent of the project is to remove the existing concrete slab and a portion of the existing concrete abutments to allow for the installation of a new, three-sided, precast concrete frame on precast concrete footings. The south abutment of the bridge will be supported on a pile cap with micropiles, while the north abutment will be supported on a concrete spread footing. The proposed bridge has an out-to-out width that will vary from 49’-6” at the south abutment to 40’-0” at the north abutment, with two (2) 10-foot travel lanes and a 4-foot shoulder on each edge of the roadway. The bridge will also include a 5’-6” wide sidewalk along the west side of the bridge for pedestrians.
Location:
  • Town of Erving
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $2,313,889.68
    Estimated Total Federal Participating Construction Cost: $2,629,156.16
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: PS&E Received (as of 03/14/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: ERVING
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • MPO Project (TEC) Score 40/100.
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $1,759,632.80
    State Cost: $439,908.20
    Total Cost: $2,199,541.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/23/2022
    Project Need Form PNF Approved 07/08/2022
    Project Initiation Form PIF Entered 08/23/2022
    Project Initiation Form PIF Approved 08/19/2022
    Project Initiation Form PRC Submitted 09/09/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Management
    100% Design 100% Package Received 10/31/2024
    25% Design 25% Package Received 11/21/2023
    25% Design 25% Package Approved 03/18/2024
    25% Design Design Public Hearing 04/18/2024
    75% Design 75% Package Received 06/07/2024
    Final Design PS&E Received 03/14/2025