Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- BRIDGE PRESERVATION, B-16-066 (38D), CAMBRIDGE STREET OVER MBTA
This bridge preservation project involves deck repair or replacement and related work, including any required superstructure repairs, guardrail and barrier, curb and sidewalk, drainage, signage and pavement markings, and minor safety improvements as required.
Location:
  • City of Boston
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Christopher I Cameron
    Estimated Total Contract Cost: $15,074,000.00
    Estimated Total Federal Participating Construction Cost: $15,895,900.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 04/05/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $13,305,600.00
    State Cost: $3,326,400.00
    Total Cost: $16,632,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/26/2022
    Project Need Form PNF Approved 08/26/2022
    Project Initiation Form PIF Entered 08/26/2022
    Project Initiation Form PIF Entered 12/21/2022
    Project Initiation Form PIF Approved 08/26/2022
    Project Initiation Form PRC Submitted 08/26/2022
    Project Initiation Form PRC Submitted 12/21/2022
    Project Review Committee PRC Tabled 09/15/2022
    Project Review Committee PRC Approved 12/21/2022
    Project Management
    Consultant Contract Process Scope to DE 04/05/2023