Project Description: |
SALEM- RECONSTRUCTION OF BRIDGE STREET (ROUTE 107), FROM FLINT STREET TO 150 FEET WEST OF WASHINGTON STREET
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Summer 2027 |
Project Manager: | Shahpar Negah![]() |
Estimated Total Contract Cost: | $10,076,104.80 |
Estimated Total Federal Participating Construction Cost: | $11,218,837.20 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | Design Public Hearing (as of 07/29/2025 ) |
|
Bridges |
|
|
|