Project Description: |
LEOMINSTER- UXBRIDGE- BRIDGE PRESERVATION- L-08-038, U-02-047, U-02-048, U-02-058, U-02-063
This project will perform a series of bridge preservation activities including wearing surface replacement, deck repairs, joint replacement, substructure repairs, steel repairs and painting on bridges in the following locations: Leominster - Johnny Appleseed Lane over I-190; Uxbridge - Pond Street, Mill Street and Coppola Street over Route 146.
|
Location: |
|
Construction Begins: | Spring 2023 |
Resident Engineer: | Yasser Talib |
Construction Bid Price: | $6,132,379.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|